CPEC a sinking ship

With Pakistan unable to iron out systemic issues to allow smooth working of Chinese companies, and not in a position to honour its financial commitments, Beijing has slowed down investment on the flagship CPEC-part of its global Belt and Road Initiative (BRI)…writes Rahul Kumar

 Pakistan is giving more time to China to build power plants, as key infrastructure projects-the icons of the mega China Pakistan Economic Corridor (CPEC) face big delays.

The timeline for five projects-Suki Kinari Hydropower Project, Karot Hydropower Project, Tel project at Thar block-II, Thal Nova Thar block-II and Thar block-I have been extended, says The Express Tribune.

The projects have a combined power producing capacity of 3,600 MW.

The fourth Pak-China Relations Steering Committee meeting, chaired by Planning Minister Asad Umar on Wednesday, took the decision to extend the deadline due to slowdown of work, covid-related delays and strikes.

The committee found that not just power projects, but even road projects have been delayed. Work on the Quetta-Zhob Road project had been halted under orders from the Islamabad High Court while the Karakoram Highway Thakot-Raikot also remained stopped.

‘US, India make attempts to manoeuvre Pak out of CPEC’

Other issues holding up CPEC projects include delays in visa processing for Chinese nationals. The committee said that Pakistan is holding up the visa applications of nearly 90,000 Chinese nationals. Chinese companies have told the Pakistan government that their employees should be provided work visas instead of business visas which lead to penalties and bans on Chinese citizens.

Individual Chinese companies have run into policy hurdles of different kinds. Many firms have paid for electricity and gas connections but have not received the services despite months of delay. Other companies have applied for allotment of land but have not been given clearance.

Despite an iron-clad partnership in almost all spheres of their relationship, the two allies face a multitude of challenges in implementing CPEC projects. The $62 billion CPEC includes power generation projects, road and rail networks, industrial parks, special economic zones as well as the construction of the multi-use Gwadar port in Balochistan.

China is also providing financing for the projects, which entails high interest rates and overhead charges that include debt servicing and guaranteed returns for Chinese companies. Pakistan has been unable to pay these extraordinarily high returns to Chinese companies complicating relations between the government and Chinese firms.

Another roadblock that Pakistan is unable to surmount is the non-payment of nearly $1.4 billion, equivalent of Rs 230 billion, to Chinese power companies for the electricity generated under CPEC projects. In September, Planning Minister Asad Umar had said that the government was looking at ways to clear $1.4 billion owed to the Chinese power producers.

That payment has not been made till now partly because Pakistan is unable to recover adequate dues from retail consumers. Also, Pakistan wants to renegotiate the terms of contract and guarantees with Chinese power companies as it finds these to be on the higher side.

With Pakistan unable to iron out systemic issues to allow smooth working of Chinese companies, and not in a position to honour its financial commitments, Beijing has slowed down investment on the flagship CPEC-part of its global Belt and Road Initiative (BRI).

Other reasons for Beijing’s unhappiness include security. Chinese nationals have faced several attacks, including the targeting of Chinese ambassador Nong Rong in April at the Serena hotel in Balochistan’s capital Quetta. Chinese nationals told the BBC that they live in fear as they had to face attacks in many Pakistani cities.

Earlier this year, militants attacked a convoy of Chinese engineers, killing nine of them working on the Dasu hydropower project in Khyber Pakhtunkhwa, which gave another excuse to Chinese firms to stop work. Chinese firms want compensation for their dead employees, which has not been settled by Pakistan as yet.

Even though Pakistan is putting up a brave front on the CPEC projects, not all is well either on the projects or in the diplomatic domain. In November, Pakistan had requested China to restart work on the stalled CPEC projects, but there has been no response from China or its companies till now.

China seems to be in no mood to relent till Pakistan coughs up the money. With the Pakistani economy dwindling, the CPEC is beginning to look like a sinking ship for both Beijing and Islamabad.

(The content is being carried under an arrangement with indianarrative.com)

ALSO READ: INTERVIEW: ‘Baloch People Angry With CPEC, Pak Govt’

Previous Story

Peshawar remembers the martyred students at Army Public School

Next Story

Spike in number of countries providing visa-on-arrival for Indians

Latest from -Top News

Trump: Khamenei an ‘Easy Target’

As the conflict between Iran and Israel entered its fifth day and continues to escalate, Trump also called for Iran’s “UNCONDITIONAL SURRENDER”….reports Asian Lite News US President Donald Trump on Tuesday claimed

India Evacuates Students from Tehran

The Ministry also said that the Indian Embassy is continuously in touch with the community to provide all feasible assistance….reports Asian Lite News Amid rising tensions between Israel and Iran, India has

Trump: Get Out of Tehran Now!

The US President also announced that he would cut short his visit to the Group of 7 (G7) summit in Canada to closely monitor the situation …reports Asian Lite News US President

Iran Hits Key Israeli Oil Facility

Three company employees were killed in the pre-dawn attack on Monday night, which ignited fires at the strategic complex….reports Asian Lite News Bazan, Israel’s largest oil refinery company, announced that all of
Go toTop

Don't Miss

Coronavirus infects 295 children in Balochistan

70 people succumbed to the virus in the last 24

Wind storm shakes Pakistan

The district administration of all areas of the province was